In a preliminary solar layout study, moving the pooling substation inwards shortened the aggregate 33 kV feeder route from about 66 km to 34 km. The same option introduced about 1.6 km of higher-voltage line extension and displaced array tables. Those three figures belong in the same comparison.
Read the trade-off
The grid-line-end location saved the outgoing extension. The more central location brought the substation closer to several large generation blocks. Neither distance alone captures the works involved. Access, crossings, land for the substation and the energy contribution of displaced tables may change the choice.
Record the adopted basis
Show each alternative against the same block layout, with the outgoing line and internal network measured separately. When the project retains one option, carry its feeder quantities into the estimate. Keeping the cable allowance from a different location creates a misleading budget.