A 1 km feeder corridor can require more than 1 km of cable. Two parallel three-core runs following the same corridor already require 2 km of three-core cable before allowances. The trench, cable and conductor measurements each answer a different procurement question.
Rebuild the estimate
List the origin, destination, measured route, cable construction and number of parallel runs. Apply any explicit allowance after multiplying the route by the runs. For a purchased three-core cable, the three internal cores do not triple the ordered length of the assembled cable.
Find the source of a mismatch
Check whether the comparison includes the same substations and package boundary. Then check route assumptions, parallel runs and allowances in that order. This often explains a variance more clearly than applying one percentage adjustment to every feeder.