Renewable Projects may face curtailment

Published by firstgreen on

 

RE Absorption on critical days

 

Sl.

No.

Scenario

Day

RE

absorption

1

Peak Day / Max Energy demand day

7th October, 2029

99.74 %

2

Maximum VRE (Wind+Solar) generation day

3rd July, 2029

85.32 %

3

Maximum Solar generation day

25th March, 2030

89.56 %

4

Minimum Solar generation day

8th August, 2029

100%

5

Minimum Energy demand day

14th December, 2029

97.19 %

6

Minimum VRE (Wind+Solar) generation day

1st February, 2030

100%

7

Maximum Variation in demand day

27th January, 2030

100%

8

Maximum Variation in Net demand day

26th October, 2029

86.76 %

 

It has been observed that the RE absorption is around 85.32 % on 3rd July, 2029 (i.e. the Maximum VRE day). In order to study the impact of lowering the minimum technical load of coal based plants on RE absorption, a study has been carried out by reducing the minimum technical load of coal plants from 55% to 50%, 45% and 40% on this day. The impact of reducing the minimum technical load on RE absorption on Maximum VRE day is shown in the 

 

During the course of the above analysis, it was observed that RE absorption can be increased with a reduction in minimum technical load, thus increasing flexible operation of thermal power plants. However, this entails investment for technological upgradation in coal-based power plants. An increase of approximately 1.5 % in the RE absorption was observed for every step of 5

% reduction in minimum technical load of coal-based capacity on this day. However, the impact on RE absorption by reducing the minimum technical load of coal-based plants may vary from day to day depending on the coal-based capacity on bar and available RE generation.

                                    <img width="940" height="536" src="https://dcsgroups.in/temp/wp-content/uploads/2020/09/Screen-Shot-2020-09-18-at-12.47.51-AM.png" alt="" srcset="https://i0.wp.com/www.firstgreen.co/wp-content/uploads/2020/09/Screen-Shot-2020-09-18-at-12.47.51-AM.png?w=940&amp;ssl=1 940w, https://i0.wp.com/www.firstgreen.co/wp-content/uploads/2020/09/Screen-Shot-2020-09-18-at-12.47.51-AM.png?resize=768%2C438&amp;ssl=1 768w, https://i0.wp.com/www.firstgreen.co/wp-content/uploads/2020/09/Screen-Shot-2020-09-18-at-12.47.51-AM.png?resize=470%2C268&amp;ssl=1 470w, https://i0.wp.com/www.firstgreen.co/wp-content/uploads/2020/09/Screen-Shot-2020-09-18-at-12.47.51-AM.png?resize=150%2C86&amp;ssl=1 150w" sizes="(max-width: 940px) 100vw, 940px" />