LEED Certification for Homes – EQ CREDIT: CONTAMINANT CONTROL

Published by firstgreen on

Requirements

HOMES

Option 1. Walk-off Mats (0.5 point)

At each primary entryway from the outdoors, design and install a permanent walk-off mat that is at least 4 feet (1.2 meters) long and allows access for cleaning (e.g., grating with catch basin). Permanent walk-off mats are required only for primary exterior entryways, but nonpermanent walk-off mats are strongly recommended for other entryways.

For regularly used common exterior entryways in multifamily buildings, install permanent systems that are at least 10 feet long (3 meters) in the primary direction of travel to capture dirt and particulates.

Acceptable entryway systems include permanently installed grates, grilles, and slotted surfaces that allow for cleaning underneath. Roll-out mats are acceptable only if maintained on a weekly basis by a contracted service organization.

AND/OR

Option 2. Shoe Removal and Storage (0.5 point)

Design a shoe removal and storage space near the primary entryway, separated from living areas.

This space must be a permanent architectural feature and it must be large enough to accommodate a bench and at least two pairs of shoes per bedroom and must not have conventional carpet.

Carpet tile is acceptable if it’s specifically designed for entryway systems or similar use, including performance attributes equivalent to other acceptable entryway systems.

For multifamily buildings, design a shoe removal and storage space at each residential unit’s primary entrance.

AND/OR

Option 3. Preoccupancy Flush (0.5 points)

At installation, seal all permanent ducts and vents to minimize contamination from construction. Remove seals after all phases of construction are completed.

After construction ends and before occupancy, flush the home with fresh air, according to the following guidelines:

  • Remove any dust and debris from ducts.  
  •  Flush the entire home for 48 hours, keeping all windows and interior doors open; the 48 hours may be nonconsecutive if necessary.  
  • Keep all windows open and run a fan (e.g., HVAC system fan) continuously, or flush the home with all HVAC fans and exhaust fans operating continuously at the highest flow rate.

For multifamily buildings, the requirements apply only to all in-unit spaces.

Projects that earn the EPA Indoor airPLUS label automatically meet the requirements of Option 3. AND/OR

Option 4. Air Testing (1 point)

After construction ends and before occupancy, but under ventilation conditions typical for occupancy, conduct baseline indoor air quality testing using protocols consistent with the methods listed in Table 1.

Project teams must follow either the Use current versions of ASTM standard methods, EPA compendium methods, or ISO methods, as indicated.

Demonstrate that contaminants do not exceed concentration levels listed in Table 1.

Table 1. Maximum concentration levels, by contaminant and testing method

      Contaminant    Maximum concentrationMaximum concentration (Healthcare only)    ASTM and U.S. EPA methods      ISO method
Formaldehyde27 ppb16.3 ppbASTM D5197; EPA TO-11 or EPA Compendium Method IP-6ISO 16000-3
Particulates (PM10 for all buildings; PM2.5 for buildings in EPA nonattainment areas)PM10: 50 micrograms per cubic meter PM2.5: 15 micrograms per cubic meter20 micrograms per cubic meterEPA Compendium Method IP-10ISO 7708
Ozone (for buildings in EPA nonattainment areas)0.075 ppm0.075 ppmASTM D5149 – 02ISO 13964
Total volatile organic compounds (TVOCs)500 micrograms per cubic meter200 micrograms per cubic meterEPA TO-1, TO- 15, TO-17, or EPA Compendium Method IP-1ISO 16000-6
Target chemicalsCDPH StandardCDPH StandardASTM D5197;ISO 16000-3,
listed in CDPH Standard Method v1.1, Table 4-1, except formaldehydeMethod v1.1– 2010, Allowable Concentrations, Table 4-1Method v1.1– 2010, Allowable Concentrations, Table 4-1EPA TO-1, TO- 15, TO-17, or EPA Compendium Method16000-6
Carbon monoxide (CO)9 ppm; no more than 2 ppm above outdoor levels9 ppm; no more than 2 ppm above outdoor levelsEPA Compendium Method IP-316000-6

ppb = parts per billion; ppm = parts per million; μg/cm = micrograms per cubic meter

Conduct all measurements before occupancy but during normal occupied hours, with the building ventilation system started at the normal daily start time and operated at the minimum outside air flow rate for the occupied mode throughout the test.

The number of sampling locations depends on the size of the building and number of ventilation systems but must include the entire building and all representative situations. Include areas with the least ventilation and greatest presumed source strength.

Collect air samples between 3 and 6 feet (900 and 1 800 millimeters) from the floor to represent the breathing zone of occupants over a minimum four-hour period.

Measure particulate concentrations by a gravimetric method. Hand-held or real-time instruments are not acceptable unless they are calibrated on site against the standard gravimetric method.

For each sampling point where the concentration exceeds the limit, take corrective action and retest for the noncompliant contaminants at the same sampling points. Repeat until all requirements are met.

Refer to CA Section 01350, Appendix B, New Single-Family Residence Scenario, for air-testing guidance.

MIDRISE

Option 1. Walk-off Mats (0.5 point)

At each unit’s primary entryway from the outdoors, design and install a permanent walk-off mat that is at least 4 feet (1.2 meters) long and allows access for cleaning (e.g., grating with catch basin).

For regularly used common exterior entryways in multifamily buildings, install permanent systems that are at least 10 feet (3 meters) long in the primary direction of travel to capture dirt and particulates.

Acceptable entryway systems include permanently installed grates, grilles, and slotted surfaces that allow for cleaning underneath. Roll-out mats are acceptable only if maintained on a weekly basis by a contracted service organization.

AND/OR

Option 2. Shoe Removal and Storage (0.5 point)

In each unit, design a shoe removal and storage space near the entryway, separated from living areas. This space must be a permanent architectural feature, it may not have wall-to-wall carpeting, and it must be large enough to accommodate a bench and at least two pairs of shoes per bedroom.

AND/OR

Option 3. Preoccupancy flush (0.5 point)

The Preoccupancy Flush can be awarded if the requirements are only met for all in-unit spaces.

At installation, seal all permanent ducts and vents to minimize contamination from construction. Remove seals after all phases of construction are completed.

After construction ends and before occupancy, flush the home with fresh air, according to the following guidelines:

  •   Remove any dust and debris from ducts.  
  •  Flush the entire home, keeping all interior doors open for 48 hours; the hours may be nonconsecutive if necessary.  
  •  Keep all windows open and run a fan (e.g., HVAC system fan) continuously, or flush the home with all HVAC fans and exhaust fans operating continuously at the highest flow rate.

For multifamily buildings, the requirements apply only to all in-unit spaces. AND/OR

Option 4. Air Testing (1 point)

After construction ends and before occupancy, but under ventilation conditions typical for occupancy, conduct baseline indoor air quality testing using protocols consistent with the methods listed in Table 1.

Project teams must follow either the current versions of ASTM standard methods, EPA compendium methods, or ISO methods, as indicated.

Demonstrate that contaminants do not exceed concentration levels listed in Table 1.

Table 2. Maximum concentration levels, by contaminant and testing method

      Contaminant    Maximum concentrationMaximum concentration (Healthcare only)    ASTM and U.S. EPA methods      ISO method
Formaldehyde27 ppb16.3 ppbASTM D5197; EPA TO-11 or EPA Compendium Method IP-6ISO 16000-3
Particulates (PM10 for all buildings; PM2.5 for buildings in EPA nonattainment areas)PM10: 50 micrograms per cubic meter PM2.5: 15 micrograms per cubic meter20 micrograms per cubic meterEPA Compendium Method IP-10ISO 7708
Ozone (for buildings in EPA0.075 ppm0.075 ppmASTM D5149 – 02ISO 13964
nonattainment areas)    
Total volatile organic compounds (TVOCs)500 micrograms per cubic meter200 micrograms per cubic meterEPA TO-1, TO- 15, TO-17, or EPA Compendium Method IP-1ISO 16000-6
Target chemicals listed in CDPH Standard Method v1.1, Table 4-1, except formaldehydeCDPH Standard Method v1.1– 2010, Allowable Concentrations, Table 4-1CDPH Standard Method v1.1– 2010, Allowable Concentrations, Table 4-1ASTM D5197; EPA TO-1, TO- 15, TO-17, or EPA Compendium MethodISO 16000-3, 16000-6
Carbon monoxide (CO)9 ppm; no more than 2 ppm above outdoor levels9 ppm; no more than 2 ppm above outdoor levelsEPA Compendium Method IP-3ISO 4224

ppb = parts per billion; ppm = parts per million; μg/cm = micrograms per cubic meter

Conduct all measurements before occupancy but during normal occupied hours, with the building ventilation system started at the normal daily start time and operated at the minimum outside air flow rate for the occupied mode throughout the test.

The number of sampling locations depends on the size of the building and number of ventilation systems but must include the entire building and all representative situations. Include areas with the least ventilation and greatest presumed source strength.

Collect air samples between 3 and 6 feet (900 and 1 800 millimeters) from the floor to represent the breathing zone of occupants over a minimum four-hour period.

Measure particulate concentrations by a gravimetric method. Hand-held or real-time instruments are not acceptable unless they are calibrated on site against the standard gravimetric method.

For each sampling point where the concentration exceeds the limit, take corrective action and retest for the noncompliant contaminants at the same sampling points. Repeat until all requirements are met.

Refer to CA Section 01350, Appendix B, New Single-Family Residence Scenario, for air-testing guidance.