SCHEME FOR SETTING UP OF 1000 MW OF GRID CONNECTED SOLAR PV POWER PROJECTS BY CPSUS AND GOVT. ORGANIZATIONS UNDER VARIOUS CENTRAL/ STATE SCHEMES/SELF USE/3RD PARTY SALE/MERCHANT SALE WITH VIABILITY GAP FUNDING (VGF) UNDER PHASE-II OF JNNSM.

Published by firstgreen on

The Ministry launched the above scheme in January 2015 , the Scheme is closed for new sanctions. Under this Scheme, MNRE has sanctioned around 882 MW grid-connected solar PV power plant capacity to   9 CPSUs/Govt. Organizations. As of 31.12.2019, all the sanctioned 882 MW capacity solar PV projects have been commissioned.

(iii) As on 31.12.2019, VGF of around Rs. 795 crores (including SECI’s charges) has already been released to SECI for onward disbursal to CPSUs/Govt. Organisations who have set up solar PV power projects under the Scheme.