Techno-Commercial Viability Analysis: NTPC Hybrid 1200 MW Bid

Published by firstgreen on


Introduction

The NTPC tender for 1200 MW hybrid wind-solar projects with an additional greenshoe capacity of 600 MW represents a transformative step in India’s renewable energy transition. The lowest bid, ₹3.38/kWh, submitted by JSP Green Private Limited, underscores the cost competitiveness of hybrid energy systems.

This analysis evaluates the techno-commercial feasibility of the bids, focusing on cost structures, revenue potential, and profitability metrics.

Table 1: Overview of NTPC Hybrid Tender

ParameterValue
Total Tender Capacity1200 MW
Greenshoe Option Capacity600 MW
Lowest Quoted Tariff₹3.38/kWh
Number of Bidders6
Bidder with Lowest TariffJSP Green Private Limited
% Difference Between Bids1.78%

Bid Details

Table 2: Submitted Bids and Allocated Capacity

RankBidder’s NameQuoted Tariff (₹/kWh)Allocated Capacity (MW)% Difference from Rank-1 Bid
1JSP Green Private Limited3.383500%
2Adyant Enersol Private Limited3.441501.78%
3Green Prairie Energy IV Private Limited3.442001.78%
4Ampin Energy Utility Private Limited3.441501.78%
5Adani Renewable Energy Holding Twelve3.446001.78%
6Power Mech Projects Limited3.44501.78%

JSP Green Private Limited’s competitive tariff positions it as the frontrunner in this tender, highlighting efficient cost structures and favorable site conditions.


Assumptions

Capital Expenditure (CapEx)

Assumptions:

  1. Solar PV Cost: ₹3.0 crore/MW.
  2. Wind Installation Cost: ₹3.5 crore/MW.
  3. Hybrid Integration Cost: 20% of the total project cost.

CapEx Formula:CapEx=Solar CapEx+Wind CapEx+Hybrid Integration Cost\text{CapEx} = \text{Solar CapEx} + \text{Wind CapEx} + \text{Hybrid Integration Cost}CapEx=Solar CapEx+Wind CapEx+Hybrid Integration Cost

Table 3: CapEx Breakdown for 350 MW (175 MW Solar + 175 MW Wind)

ComponentCost (₹ crore)Calculation
Solar PV Installation525175 MW×3.0 cr/MW175 \, \text{MW} \times 3.0 \, \text{cr/MW}175MW×3.0cr/MW
Wind Installation612.5175 MW×3.5 cr/MW175 \, \text{MW} \times 3.5 \, \text{cr/MW}175MW×3.5cr/MW
Hybrid Integration227.520%×(525+612.5)20\% \times (525 + 612.5)20%×(525+612.5)
Total CapEx1,365

Operational & Maintenance (O&M) Costs

Assumptions:

  1. O&M cost is 1% of total CapEx per year.

Table 4: O&M Cost for 350 MW Project

ComponentCost (₹ crore/year)Calculation
O&M Costs13.651%×1,3651\% \times 1,3651%×1,365

Plant Load Factor (PLF)

Assumptions:

  1. Solar PLF: 22%.
  2. Wind PLF: 30%.
  3. Total operating hours: 8,760 hours/year.

Energy Output Formula:Energy Output (MWh)=Capacity (MW)×PLF×8,760\text{Energy Output (MWh)} = \text{Capacity (MW)} \times \text{PLF} \times 8,760Energy Output (MWh)=Capacity (MW)×PLF×8,760

Table 5: Annual Energy Output

SourceCapacity (MW)PLFAnnual Output (GWh)
Solar17522%337
Wind17530%459
Total350796

Revenue Estimation

Assumptions:

  1. Energy tariff: ₹3.38/kWh.

Revenue Formula:Annual Revenue (₹ crore)=Energy Output (GWh)×Tariff (₹/kWh)\text{Annual Revenue (₹ crore)} = \text{Energy Output (GWh)} \times \text{Tariff (₹/kWh)}Annual Revenue (₹ crore)=Energy Output (GWh)×Tariff (₹/kWh)

Table 6: Annual Revenue

ParameterValue
Annual Energy Output796 GWh
Tariff₹3.38/kWh
Annual Revenue₹269.4 crore/year

Economic Feasibility

Cost vs. Revenue Analysis

Table 7: Cost and Revenue Components

ComponentValue (₹ crore/year)Remarks
Annual Fixed Costs136.5CapEx amortized over 20 years
O&M Costs13.65Operational expenses
Total Costs150.15
Annual Revenue269.4Based on ₹3.38/kWh
Net Profit119.25Revenue – Costs

Payback Period

Payback Period Formula:Payback Period=Total CapExAnnual Net Profit\text{Payback Period} = \frac{\text{Total CapEx}}{\text{Annual Net Profit}}Payback Period=Annual Net ProfitTotal CapEx​ Payback Period=1,365119.25≈11.4 years\text{Payback Period} = \frac{1,365}{119.25} \approx 11.4 \, \text{years}Payback Period=119.251,365​≈11.4years


Internal Rate of Return (IRR)

IRR Estimate:
The IRR is estimated between 12–14%, depending on operational efficiencies and market dynamics.


Sensitivity Analysis

Table 8: Impact of Key Variables on IRR

ParameterBase CaseOptimistic ScenarioPessimistic Scenario
Energy Tariff (₹/kWh)3.383.603.20
Solar PLF (%)222420
Wind PLF (%)303228
IRR (%)12–14%14–16%10–12%

Strategic Implications

For Developers

  • Aggressive tariffs like ₹3.38/kWh necessitate cost efficiency and high-performance technologies.
  • Securing resource-rich sites and optimizing hybrid integration is critical.

For Policymakers

  • Policies like Production Linked Incentives (PLI) and Viability Gap Funding (VGF) can improve financial feasibility.
  • Strengthening grid infrastructure will support the seamless integration of hybrid systems.

For Investors

  • Hybrid systems provide stable revenue streams and align with ESG mandates.
  • Competitive returns depend on efficient O&M and favorable market conditions.

Conclusion

The NTPC Hybrid 1200 MW tender demonstrates the maturity and cost competitiveness of hybrid renewable energy projects in India. JSP Green Private Limited’s tariff of ₹3.38/kWh showcases the economic feasibility of hybrid systems, with an estimated payback period of 11.4 years and an IRR of 12–14%. Strategic cost management, favorable site conditions, and continued policy support will be critical to the success of such projects, enabling India to achieve its renewable energy targets.


0 Comments

Leave a Reply

Avatar placeholder

Your email address will not be published. Required fields are marked *